Work Order Duration Calculation

Tool: Code Explainer

Created: 03/24/2024

Prompt

Date_Dif_Order = 
VAR Var1 =
    CALCULATE (
        MIN ( Table1[ActualStartDate] ),
        ALLEXCEPT ( Table1, Table1[Work Order] )
    )
VAR Var2 =
    CALCULATE (
        MAX ( Table1[ActualFinishDate] ),
        ALLEXCEPT ( Table1, Table1[Work Order] )
    )
RETURN
    DATEDIFF ( Var1, Var2, DAY )

Code Explanation

The provided code calculates the difference in days between the earliest start date (ActualStartDate) and the latest finish date (ActualFinishDate) for each work order in a table.

  1. VAR Statements:

    • VAR Var1: Calculates the minimum ActualStartDate for each Work Order by utilizing the MIN function with CALCULATE and ALLEXCEPT to remove filters except for Work Order.
    • VAR Var2: Calculates the maximum ActualFinishDate for each Work Order using the MAX function in a similar manner as Var1.
  2. RETURN Statement:

    • The RETURN section uses the DATEDIFF function to find the difference in days between Var1 and Var2. The DAY parameter specifies that the difference should be in days.

Key Concepts

  • CALCULATE Function: Modifies the filter context within which the calculation is being performed.
  • ALLEXCEPT Function: Preserves the filter on Work Order column while removing other filters on the same table (Table1).
  • DATEDIFF Function: Calculates the difference between two dates in the specified time unit (in this case, days).

Additional Example

If you want to calculate the difference in hours between Var1 and Var2 instead of days, you can modify the RETURN statement:

RETURN
    DATEDIFF ( Var1, Var2, HOUR )

This adjustment changes the time unit from days to hours for the calculation.

Visual Date Difference Order Logic

Tool: Logic Visualizer

Created: 03/24/2024

Prompt

Date_Dif_Order = 
VAR Var1 =
    CALCULATE (
        MIN ( Table1[ActualStartDate] ),
        ALLEXCEPT ( Table1, Table1[Work Order] )
    )
VAR Var2 =
    CALCULATE (
        MAX ( Table1[ActualFinishDate] ),
        ALLEXCEPT ( Table1, Table1[Work Order] )
    )
RETURN
    DATEDIFF ( Var1, Var2, DAY )

Visual Representation of Date_Dif_Order Logic

Pseudocode:

1. Set Date_Dif_Order variable
2. Define Var1 as the minimum Actual Start Date for each Work Order
3. Define Var2 as the maximum Actual Finish Date for each Work Order
4. Calculate the difference in days between Var1 and Var2
5. Return the calculated date difference as Date_Dif_Order

Annotations:

  • Date_Dif_Order: Variable to store the calculated date difference.
  • Var1: Variable holding the minimum Actual Start Date for each Work Order.
  • Var2: Variable holding the maximum Actual Finish Date for each Work Order.
  • CALCULATE: Function used to manipulate filter context.
  • MIN, MAX: Functions to find the minimum and maximum values.
  • ALLEXCEPT: Function to remove filters except for the specified column.
  • DATEDIFF: Function to calculate the difference in days between two dates.